The Sydney Opera House is a multi-venue performing arts centre on Bennelong Point in Sydney, New South Wales, Australia. It was conceived and largely built by Danish architect Jørn Utzon, who in 2003 received the Pritzker Prize, architecture's highest honour. The citation stated

The Opera House was made a UNESCO World Heritage Site on 28 June 2007. It is one of the 20th century's most distinctive buildings, and one of the most famous performing arts centres in the world.

The Sydney Opera House is situated on Bennelong Point in Sydney Harbour, close to the Sydney Harbour Bridge. It sits at the north-eastern tip of the Sydney central business district (the CBD), surrounded on three sides by the harbour (Sydney Cove and Farm Cove), and neighboured by the Royal Botanic Gardens.

Contrary to its name, the building houses several separate venues rather than a single opera theatre, the two main venues, the Opera Theatre and the Concert Hall, being housed in the two larger sets of shells. The Sydney Opera House is a major presenting venue for Opera Australia, The Australian Ballet, the Sydney Theatre Company and the Sydney Symphony, as well as hosting many touring productions in a variety of performance genres, and is a major tourist attraction. It is administered by the Sydney Opera House Trust, under the New South Wales Ministry of the Arts.

Description

The Sydney Opera House is a modern expressionist design,with a series of large precast concrete 'shells', each composed of sections of a hemisphere of the same radius, forming the roofs of the structure, set on a monumental podium. The building covers 1.8 hectares (4.5 acres) of land, and is 183 metres (605 ft) long and 120 metres (388 ft) wide at its widest point. It is supported on 588 concrete piers sunk as much as 25 metres below sea level. Its power supply is equivalent to that of a town of 25,000 people, and is distributed by 645.5 kilometres (401 miles) of electrical cable.

The roofs of the House are covered in a subtle chevron pattern with 1,056,006 glossy white and matte cream colored Swedish-made tiles from Höganäs AB, though from a distance the shells appear a uniform white. Despite the tiles' self-cleaning nature, they do require periodic maintenance and replacement.

The Concert Hall is located within the western group of shells, the Opera Theatre within the eastern group. The scale of the shells was chosen to reflect the internal height requirements, with low entrance spaces, rising over the seating areas and up to the high stage towers. The minor venues (Drama Theatre, Playhouse, and The Studio) are located beneath the Concert Hall, as part of the western shell group. A much smaller group of shells set to one side of the Monumental Steps houses the Bennelong Restaurant. Although the roof structures of the Sydney Opera House are commonly referred to as shells (as they are in this article), they are in fact not shells in a strictly structural sense, but are instead precast concrete panels supported by precast concrete ribs.

Apart from the tile of the shells, and the glass curtain walls of the foyer spaces, the building's exterior is largely clad with aggregate panels composed of pink granite quarried in Tarana. Significant interior surface treatments also include off-form concrete, Australian white birch plywood supplied from Wauchope in northern New South Wales, and brush box glulam.

Performance venues and facilities

The Opera House houses the following performance venues:

  • The Concert Hall , with 2,678 seats, is the home of the Sydney Symphony, and used by a large number of other concert presenters. It contains the Sydney Opera House Grand Organ, the largest mechanical tracker action organ in the world, with over 10,000 pipes.
  • The Opera Theatre , a proscenium theatre with 1,507 seats, is the Sydney home of Opera Australia and The Australian Ballet.
  • The Drama Theatre , a proscenium theatre with 544 seats, is used by the Sydney Theatre Company and other dance and theatrical presenters.
  • The Playhouse , an end-stage theatre with 398 seats.
  • The Studio , a flexible space, with a maximum capacity of 400 people, depending on configuration.
  • The Utzon Room , a small multi-purpose venue, seating up to 210. It is the only interior space to have been designed by Utzon, having been renovated in 2004 under his direction.
  • The Forecourt , a flexible open-air venue with a wide range of configuration options, including the possibility of utilising the Monumental Steps as audience seating, used for a range of community events, Live Sites, and special-occasion performances.

Other areas (for example the northern and western foyers) are also used for performances on an occasional basis. Venues at the Sydney Opera House are also used for conferences, ceremonies, and social functions. The building also houses a recording studio, five restaurants, four souvenir shops, and a guided tour operation.

Construction history

Origins

Planning for the Sydney Opera House began in the late 1940s, when Eugene Goossens, the Director of the NSW State Conservatorium of Music, lobbied for a suitable venue for large theatrical productions. The normal venue for such productions, the Sydney Town Hall, was not considered large enough. By 1954, Goossens succeeded in gaining the support of NSW Premier Joseph Cahill, who called for designs for a dedicated opera house. It was also Goossens who insisted that Bennelong Point be the site for the Opera House. Cahill had wanted it to be on or near Wynyard Railway Station in the north-west of the CBD.

A design competition was launched by Cahill on 13 September 1955 and received 233 entries, representing architects from 32 countries. The criteria specified a large hall seating 3000 and a small hall for 1200 people, each to be designed for different uses including full-scale operas, orchestral and choral concerts, mass meetings, lectures, ballet performances and other presentations. The winner, announced in 1957, was Jørn Utzon, a Danish architect. The prize was £5,000. Utzon visited Sydney in 1957 to help supervise the project. His office moved to Sydney in February 1963.

Design and construction

The Fort Macquarie Tram Depot, occupying the site at the time of these plans, was demolished in 1958, and formal construction of the Opera House began in March, 1959. The project was built in three stages. Stage I (1959–1963) consisted of building the upper podium. Stage II (1963–1967) saw the construction of the outer shells. Stage III consisted of the interior design and construction (1967–73).

Stage I: Podium

Stage I commenced on 5 December 1958, by the construction firm Civil & Civic, monitored by the engineers Ove Arup and Partners. The government had pushed for work to begin early, fearing that funding, or public opinion, might turn against them. However Utzon had still not completed the final designs. Major structural issues still remained unresolved. By 23 January 1961, work was running 47 weeks behind, mainly because of unexpected difficulties (inclement weather, unexpected difficulty diverting stormwater, construction beginning before proper construction drawings had been prepared, changes of original contract documents). Work on the podium was finally completed on 31 August 1962. The forced early start led to significant later problems, not least of which was the fact that the podium columns were not strong enough to support the roof structure, and had to be re-built.

Stage II: Roof

The shells of the competition entry were originally of undefined geometry, but early in the design process the "shells" were perceived as a series of parabolas supported by precast concrete ribs. However, engineers Ove Arup and partners were unable to find an acceptable solution to constructing them. The formwork for using in-situ concrete would have been prohibitively expensive, but because there was no repetition in any of the roof forms the construction of precast concrete for each individual section would possibly be even more expensive.

From 1957 to 1963 the design team went through at least twelve iterations of the form of the shells trying to find an economically acceptable form (including schemes with parabolas, circular ribs and ellipsoids) before a workable solution was completed. The design work on the shells involved one of the earliest uses of computers in structural analysis, in order to understand the complex forces to which the shells would be subjected. In mid-1961 the design team found a solution to the problem: the shells all being created as sections from a sphere. This solution allows arches of varying length to be cast in a common mold, and a number of arch segments of common length to be placed adjacent to one another, to form a spherical section. With whom exactly this solution originated has been the subject of s

Sydney Opera House Guided Backstage Tour

Schedule details; Pricing information; Additional information ... You'll gain "exclusive access" to areas of the Sydney Opera House normally reserved for staff ...

...

Sydney Opera House - House History Proudly Sponsored by Baulderstone

Sydney Opera House Trust formed. The Sydney Opera House Trust was previously known as the Sydney ... Stage 1 is completed in February 1963, two years behind schedule. The finished podium ...

...

Sydney Opera House: Information from Answers.com

In October 1965, Utzon gave Hughes a schedule setting out the completion dates of ... Duek-Cohen, Elias, Utzon and the Sydney Opera House, Morgan Publications, Sydney, 1967–1998.

...

Sydney Opera House - Wikipedia, the free encyclopedia

In October 1965, Utzon gave Hughes a schedule setting out the completion dates of ... Duek-Cohen, Elias, Utzon and the Sydney Opera House, Morgan Publications, Sydney, 1967–1998.

...

Sydney Opera House - LUMINOUS - Home

Sydney Opera House presents LUMINOUS – a festival of music, ideas, light and performance. Curated by Brian Eno, this inaugural year features a plethora of music alongside public ...

...

Japan Lighting Information Services,AKARI-Lighting,Sydney Opera House

... adjust a schedule to the time of the study tour. Note: Scandinavian architect Jorn Utzen wined in the competition of the world scale, and it is said that Sydney opera house was a ...

...

Sydney Opera House Guided Walking Tour

Schedule details; Pricing information; Additional information ... Go behind the scenes at the World Heritage listed Sydney Opera House, one of the world's "must ...

...

Sydney Opera House Guided Walking Tour, Sydney Cultural Tours | Viator ...

Schedule details Tour and Pricing Options Additional information Find more experiences ... Go behind the scenes at the World Heritage listed Sydney Opera House, one of the world's "must ...

...

Sydney Opera House Procurement Policy

Filming at Sydney Opera House Guidelines (as at 24 July 2009) 4 Playhouse $14,500+GST per day AND Cost-recovery (see schedule below) $3,000 +GST per half-day OR $650+GST/hr AND Cost-recovery ...

...

Sydney Opera House Tickets - Maps, Events, Seating Chart - Ticket ...

Sydney Opera House Event Schedule ... If you would like to attend an event at Sydney Opera House, Coast To Coast Tickets can ...

...